Demand lines and updates on Planned Cost values Hello, Could you please let me know if the steps described below are capturing expected behaviour? please notice column comments. I was expecting the planned cost to get updated after the changed in the PURQ (Purchase Requisition) price but the Planned Cost has not changed (row 5 in table) ID Action Prj Materials & Services window (value) Prj Monitoring window Comment 1 Add demand line (MISC. PARTS) 10,000 Planned Cost = 10,000 2 Create Project Supply Request 10,000 Planned Committed Cost = 10,000 3 Create PURQ 10,000 Planned Cost = 10,000 Planned Committed Cost = 10,000 4 Update Price Manually in PURQ (Change Price/Curr from 10 to 20) 10,000 Planned Cost = 10,000 Planned Committed Cost = 20,000 At the time of creating the PURQ the price of the provider of the external services has changed, hence the manual update on the PURQ 5 Update Planned Cost & Hours in the demand line 10,000 Planned Cost = 10,000 Planned Committed Cost = 20,000 There is no changes in the Planned Cost. The origina