Default Planned Cost driver and Progress method are both set to Connected objects.
This settings are rarely in use for estimates and progress in our company…. and our users often forget to change them… this creates a problem when you set your baseline, since it does not fetch our estimates, but try to find amounts from Connected objects.
So,
-how to change default Planned cost driver and Progress method?
That would help our endusers a lot!