Question

Planned cost on project vs part unit cost

  • July 4, 2024
  • 5 replies
  • 162 views

Forum|alt.badge.img+3

Hi All,

I’ve an issue that I’m not able to understand: i systematically have a gap between the part unit cost and the panned cost on a project. The cost of raw materials (prod structure) is missing

 

In this example we can constat the issue between a customer order and a project:

But i have the same problem withshop orders and misc demands,

 

Does anyone has an idea about this issue?

 

Thanks in advance :)

 

Antoine

5 replies

Tharindu Illangasinghe
Superhero (Partner)
Forum|alt.badge.img+16

Hi @antoine.vignon,

 

Has this been sorted now ?

If not, could you please tell me what is the “Supply Code” of the Customer Order Line you are referring to ? Cost fetched from the CO Line depends on that.


Forum|alt.badge.img+3
  • Author
  • Do Gooder (Partner)
  • 7 replies
  • August 6, 2024

Hi @Tharindu Illangasinghe  thanks for your answer :)

I get the same result with supply code = “Shop order” or “Project Inventory” i do not see any difference :-S

 


Tharindu Illangasinghe
Superhero (Partner)
Forum|alt.badge.img+16

Ok, then the Planned Cost should get retrieved from Part Costings.

Could you drop a screenshot of the Part Cost of Cost Set 1 of this Inventory Part ? Also, is it a manufactured or purchased part ?


PieterBroere
Sidekick (Partner)
Forum|alt.badge.img+7
  • Sidekick (Partner)
  • 23 replies
  • August 21, 2025

Hi

 

Was this issue solved, as we have a similar problem ?

 

Regards,


Forum|alt.badge.img
  • Do Gooder (Customer)
  • 1 reply
  • November 10, 2025

Hello,

 

There is a flag on the Copy Cost Set to Cost Set One that allows Parts with a product structure to show their total cost on Projects. If you turn this flag on, the part will then have its total cost (Accumulated Cost) show in Project Planning.