Project Spread Profile functionality in Project Forecasts
The aim of this post is to clarify the functionality of the Project Spread Profile within the IFS Budgeting and Forecasting module. Refer to the following example The objective is to allocate USD 10,000 across the activity dates, which span from August 1, 2022, to November 8, 2022. This allocation follows a profile comprising five intervals with distinct percentage distributions of 0%, 10%, 20%, 30%, and 40%, respectively. We need to compute the specific spread amount per period from 2022-08 to 2022-11. Please note: The spreading calculation takes into account only working days based on the connected calendar to the project. In this instance, the connected calendar assumes 8x7 (meaning all seven days of the week are considered working days). The rule of thumb is to select only the working days during the period (start and date dates). The connected calendar to the project is referred. Project Forecast Lin with ETC and Start and End Dates Project Spread Profile with specific % distribut