Project activity is connected to a work order. Under unfinished activity work, I can see ‘’Some object is reporting committed cost to the activity. Analyze which object that reports committed cost.’’
Cost is related to Materials CRE.
How can I clear this up to close the project activity?
Thank you in advance.
Best answer by Tharindu Illangasinghe
Hi @Kavinda_Jay,
Perhaps some erroneous costs are hanging in the Project connections.
Execute the below job if you have not done it already. This is should fix the matter, unless there is some cost actually reporting from the WO.