Can anyone explain the possibility of creating a demand with a revenue number on an activity without CO flow in a Project.

 

Regards,

Rasfe.

Hi @RASFE,

 

Not sure whether this is sorted already now.

 

Have you tried entering an Estimate ?

Select a Revenue type element and enter the required amount under Estimated Revenue column

 

This will show as an Estimated Revenue in the Activity.

 

 

Additionally, if you change the Planned Cost Driver of the Activity to “Estimated Cost” then the Revenue will be shown as a Planned Revenue. (I can’t see this in my version and not sure why. But you can try that out in your version). 

 

However, there is no demand object like a CO line connected here but it does show you a probable revenue to the project.

 