Transfer of Budget Allowance from one Sub-Project to another within same Project

  • August 20, 2024
  • 4 replies
  • 98 views

Forum|alt.badge.img+9
  • Sidekick (Partner)
  • 137 replies

Hi Team,

Requirement is to transfer Budget Allowance from one Sub-Project to another Sub-Project within the same Project.

I tried to use EAC Workbench functionality for Budget Transfer but currently not getting any option to add a line under Transferred To in Budget Transfer dialog box.

Please find the attached screenshot for reference.

Just wanted to know am I missing any Prerequisite setup or is this a permission issue?

 

Thank you in advance.

 

Best Regards,

Rakesh

Best answer by Tharindu Illangasinghe

Hi @Rakesh,

 

Check whether your EAC Workbench Status is “In Progress” and Forecast Status is “Preliminary”.

 

Then the option to add lines in the transfer should be visible to you.

 

4 replies

Forum|alt.badge.img+9
  • Author
  • Sidekick (Partner)
  • 137 replies
  • August 23, 2024

Hi Team,

 

Request you to please help me on this.

 

Best Regards,

Rakesh


Tharindu Illangasinghe
Superhero (Partner)
Forum|alt.badge.img+16

Hi @Rakesh,

 

Check whether your EAC Workbench Status is “In Progress” and Forecast Status is “Preliminary”.

 

Then the option to add lines in the transfer should be visible to you.

 


Forum|alt.badge.img+9
  • Author
  • Sidekick (Partner)
  • 137 replies
  • August 27, 2024

Hi @Tharindu Illangasinghe 

Thank you so much for the response.

Just a query what is the workaround if Project Forecast is approved and still we need to perform Budget Transfer??


Tharindu Illangasinghe
Superhero (Partner)
Forum|alt.badge.img+16

Hi @Rakesh,

 

You are welcome…

I don’t see a straight workaround for that, apart from demoting the Forecast back to “Preliminary” state. 

However, this may not be much practical as business will have to roll-back the number of steps done in the application, already.