We are using IFS Apps 9. While investigating why we couldn't close certain projects, I discovered that some labor hours are listed as Committed hours in "Activities." Additionally, the associated project transactions are neither approved nor have cost accounting vouchers created, even though they have been invoiced. It appears that only a few of these transactions are non-invoiceable.
Can someone clarify what is happening? The time card for the day seems accurate though. How can we avoid this in the future?