This will include the questions related to Procurement, Demand Planner, ASC, and SRM.
Recently active
Hello, Is anyone creating blanket purchase orders for long term equipment rentals or leases? Trying to avoid creating multiple PO’s for the same piece of equipment or increasing authorization limits to an amount that is well above level of authority for fleet managers. As an example, we could have a machine that cost $20,000/ month and plan to use it for 12 months. My preference would be that the PO would be written for $20,000, invoiced each month, and stay open for future months to allow for recurring charges. The way I understand the system today, is we would need to issue a PO for $240,000 to cover the entire term of the PO. If we need it for 13 months, then we would have to create another PO. We have well over 100 equipment PO’s so this can get messy if we have to write multiple PO’s for each unit.
Hi All,We have a Purchase Order that has been raised for a number of zero value “Part Order Lines”, when trying to release this order we get an error message that has not been seen before. The error message is: “Only allowed to have charged items together with Delivery Confirmation”This is not the first PO raised for zero value with this supplier, just dont understand why this order is affected.Any ideas?Many ThanksSteve
What is the best way to know the stock of an inventory part at customer? is there any screen for it?We are using IFS10 UPD11Bilal DrayiBest Regards,
Hi ThereCan anyone provide me with some info as to how this is meant to function and where, how the Set up happens in IFS Please,i have searched online documentation and was not able to find anything relevant or near Thank You so much, appreciated
Ask if anyone has noticed certain behavior in IFS 9.0, using Purchase Orders / Purchase Order Change Order.- We noticed that within the right-click option, after an approximate time of 25 or 30 Minutes the "Supersede Authorization" option disappears from the menu and only returns it when you log back into IFS.If you can help me in this case I would be infinitely grateful.Add image:
What’s the best way to cancel a partially authorized Purchase Requisition [Order Code 5] created through Project Misc Demand?
Hello, If we need some exterior operations from our suppliers, we are using Supplier material For Purchase Order Line module to ship and trace the material that our supplier needs. After reserving the necessary parts, we are using “Print Pick List for Purchase Order” which creates a “Delivery Note for supply parts”. This is great to share the information with our supplier, but sometimes our supplier sends us a Purchase Order for the required material. My question is how can I indicate our supplier’s PO number in the delivery note for supply parts ? Thank you for your help.Baran
Hello, I am working with a client on an issue where they converted from Apps 7.5 to Apps 10. They ship non-inventory material from one location to another. The shipping location is set as an internal supplier. The customer is an internal customer. The Customer site enters orders using sourcing code (Int Pur Dir). When the CO is released, a PO is created. The PO shows source (Int Cust Dir). Everything so far functions properly. I have not seen any issues with the setup of the internal customer or internal supplier. Both have the proper flags. But somewhere the initial setup missed something. Proof of concept. In Apps 7.5 system, they can still run the process listed above and everything works. Several CO’s were migrated into Apps 10. Those can be processed correctly as well. However, new CO’s in Apps10 will not complete properly. It gets stuck in Register Direct Delivery. In Apps 7.5, the Register Direct Delivery screen shows the Purch Qty to Deliver and the Inv Qty to Deliver. In the
I get the below warning when I try to release a customer orderThis customer order is from a intercompany purchase order.Any idea why do I get a warning on Sales promotion related activity while I have no sales promotions running on any of my sites ?
Hi every onewho knows that can I un-cancel a Change Request? or undo it?Regards,Kimia
I would want to prevent or hold a Purchase requisition from being “Requisition to Order” or “Requisition to Request” when the custom Boolean field “Hold” is checked.At what stage should the the custom event be triggered…Any suggestions ?
I have played with “Create S/P Req”, and I cannot get requisitions to be in the past (like in MRP).If you chooseCreate S/P Req - you will only get reqs after the DTF, but none after PTFDo not- well you don’t get any reqs Entire Horizon - you get anything after DTF and after PTF...from MRP - you do get the reqs in the Past, but the Forecast does not appear in IPAP. Help Please
Hi AllIs there a way to remove suppliers from view so that they can no-longer be used but still retain the historical data in IFS?
Document on transfer of Document Text from Purchase part to PR line to PO line.
Hi All,Good Day.Anyone has an Integration Procurement (ShipServ) Regression testing scenarios and test cases?Process is: RFQ (ShipServ) - Quote (IFS) and PO (ShipServ) - CO (IFS). Regards,VC
Hi, Let´s say we place orders for a car from a supplier. The total cost for a car is 30 usd, consisting of 10 usd for the hood and 5 usd per wheel. The car is a purchase structure.We place an order for a full car from supplier A, in order for supplier A to build the car we must supply them the wheels. The wheels we purchase from another supplier, supplier B.Now when we place a Purchase order, PO for a car, a customer order, CO is generated for us to supply supplier A with 4 wheels. This seems to be called component parts. When the car is delivered to us we receive an invoice for 10 usd. since we have provided the wheels ourselves. But in inventory transaction history the received value of the car is 30 usd. Now in part cost 10Level 1 has a car with “level unit cost” of 30 usd, and since level 2 consist of 4 wheels x 5 usd, The total cost to next level is 50 usd. The wheels are being calculated double. I don´t know how to best handle this in order for the component parts to only be cal
I am coming from a Microsoft C5 environment - here we have a very quick way to see all purchase transactions on a stock item from various suppliers. So we can “track price” for years easy in an overview. I can get a similar overview in the “Purchase Part” menu - but only in the Supplier agreement section. Now there is a _lot of parts_ with no supplier agreement. So how can I easy browse a parts purcase history and cost price when there is no supplier agreement on the part ? See screen shots below, Thanks,Uffe
I am looking for an automated way (without customization) to ensure that PRs/POs are not created when a supplier / supplier for purchase part does NOT have a PPAP document attached to it. Backup solution is a custom field that indicates if a PPAP file type is attached to the supplier or SFPP record and only allow activation if the file is attached. I am hoping there is a simpler solution.
Hi Does anyone recognise the error message (shown below) on the inter site incoming customer order(see screen shot below)? If so what is the cause of this error message? We have tried to process in inter site order with and without with single occurrence box checked. Example 2 (Single Occurrence not even ticked)
We are currently on APPS9 and moving in October to the Cloud version We are finding the Purchase Order Change Process is very clunky in the new cloud version, is there a way we can remove the need to create a change order and just make changes to the original order as per most other systems - Authorisation level is excessive on Purchase Order Change Orders - We only need it to be on increased value of order - Any help would be greatly appreciated, new to IFS - Thanks Sheila
Is there any documentation on IFS standard database tasks?
Hi all,My client is currently using IFS Apps 9 (Global Extension ) Country Solution-INDIA.When i am adding a line and selecting the sales part details in the Return Material Authorization window and when i save it i get an error "The Field Price/Base incl Tax Dmy must have a value".I am not sure why i am getting this error. Has anybody faced this error in this version of the application?Any help is appreciated and thanks in advance
Dears,I have a question about Purchase order authorization rule if I put a rule from 20000000 to 50000000 what will happen to PO above 50000000 ?is it be approved directly? Thanks.
Dear Community,I am having trouble figuring this out and may be it is because am a bit new to Custom Fields. Have also tried to read around but have failed to find a solution.I would like to move a column “Expiration Date” from a window under the Lot/Batch No pop up window into the background Transport Task window so that it shows as one of the columns. That is, whenever the user selects the Part No and Lot/Batch No then the Expiration Date (for this Part No and Lot/Batch) is auto populated.I would like it to be visible in the window behind (Transport Task)ScreenshotThank you in advance
Is there any way to chnage the PR/PO activity connection in case someone made a mistake in connection the line to the wrong actitivity in the Project Itmen Navigator ? The downside is that it also taking over the planned dates wich is causing troubles.(using IFS 9)
Already have an account? Login
No account yet? Create an account
Enter your E-mail address. We'll send you an e-mail with instructions to reset your password.