This will include the questions related to Manufacturing, Projects, Engineering, and Warehousing (WaDaCo).
Recently active
Hi There,Does anyone know how MRP_HORIZON_IN_DAYS is calculated?or which date is used as the reference point for this calculation? I am following up the case below.CS0503047I found that there is a comment from IFS side on April 9th, but they would like to know more detail because they need to verify if this parameter changes will not impact on their business operation or not. Hence they were requesting us to provide the technical document and Shiromal-san is communicating to R&D team. I am not sure if we can get the document and able to share it but at least, they would like to know which date (the exact date) is utilized for the calculation. Since our customer is planning to have Golive on May 11th and the judgement meeting is next week (April 21th) hence. This MRP slow response is one oof the bottleneck of passing criteria even though it is customer matter. I would appreciate it if we can get the answer asap. Regards,Chikako Yoshimura
Hi all,We use IFS Applications 10 and schedule shop orders using APB.I’m trying to model a finite physical constraint: we have a limited number of trolleys, which we call banks, that carry material between operations.Example routing:Operation 10 — Work centre A01, fixed 2 hours Operation 20 — Work centre A02, 1 minute per unitMaterial is loaded onto a bank at Operation 10. The same bank then moves with the material to Operation 20 and is only free again once Operation 20 is complete.So the bank should be constrained from:Operation 10 start → Operation 20 finishnot just during each individual operation.For example, if we only have two banks, APB should not allow a third order to start Operation 10 until one of the first two banks has completed Operation 20.I tried modelling this as a tool:Tool ID: BANKInstances: B01, B02Required on Operation 10 and Operation 20But APB releases the tool after Operation 10, then allocates a tool again for Operation 20. It does not appear to hold the same
We have run into an issue where shop order operations were accidentally over reported and then subsequently cancelled. However after cancelling the reports, the Operation Qty has become negative, the remaining open operations were closed, and the outside operation purchase order was cancelled. I was able to recreate this in our test environment. This issue occurs when the Adjust for Op Qty Deviation toggle is enabled and the over reported operation reports are cancelled in the incorrect order. Essentially what happened in the above screen shot was 141pc were completed through op 160. Then, 500pc were accidentally over reported on the same first 4 operations. Operator brought this to a supervisor to correct their mistake. The supervisor cancelled the operation reports, however they cancelled the report on op 50, then 75, then 110 and finally 160 which caused this compounding Deviation Qty, which in turn drove the Operation Quantities negative. If the reports get cancelled in the revers
Dears, can anyone of you point me what might cause this error when I’m trying to load Shop Orders to APB ? IFS10 App
Hi all,We are using the standard IFS Outside Operation / Subcontracting process and have a question regarding the creation and management of purchase requisitions and purchase orders.When a shop order is released, IFS automatically creates the related purchase requisitions or purchase orders for the outsourced operation, depending on the selected supply type. In practice, we often face situations where:Previous operations are delayed and the planned quantity is not yet available for outsourcing. Only part of the quantity can be shipped to the supplier due to transportation capacity constraints/ delays in previous operations. The standard approach is to split the shop order, which updates the purchase requisitions/orders and creates new requisitions/orders with a later delivery date.However, managing these splits requires significant effort because it is difficult to determine exactly:How much quantity has already been reported as Ship WIP to Supplier. How much quantity is still waitin
Hello All!Does anyone use Project transfer Borrow-Payback functionality?We have a requirement for a lending project to temporarily transfer material to a borrowing project.The lending project has a special discount and gets material at a low price and when the borrowing project procures replacement material to send back to the lending project, the price will be higher.We would expect the variance between the original material cost vs. the replacement material cost to remain on the borrowing project and that the lending project gets material transferred back at the original cost.I see that there is a screen that shows Borrow Cost, Payback Cost and a Cost difference, but I don’t know how it works or how to test it out.Does anyone know how to do such a transaction and know whether the cost difference would somehow remain on the borrowing project in a situation like this?Thank you!Doug Slater
Is it possible to estimate when improvements to conditional formatting will be available in the IFS Cloud?The options for conditional formatting in the IFS Cloud are significantly more limited compared to APPS10.The number of available colors is considerably smaller. Only the background, not the text itself, can be formatted. Text styles (bold, italic) cannot be adjusted. The available operators are also significantly restricted. We particularly miss the ability to search for parts of labels (e.g., "~pipe" for "contains pipe"). We are currently unable to replicate all the formatting options used in APPS10.Conditional formatting is a valuable tool for ensuring readability and a quick overview of tables. We hope that the familiar functionality will soon be available in the IFS Cloud as well. Best regardsJakob
Hi All,.Do we have any inbuilt report in IFS which can tell what is the waiting tine between two operations.?(historic) What I mean is it will provide detail of SO no Current operation Status ( When started) and Closed? and what is the next operation starting time so that we can see what is the waiting time between two operations? or any useful report which can tell the which operations has delayed or which job has currently delayed? etc
I have a buildable manufacturing structure/routing and a buildable disassembly structure/routing for one part number, MW-M-103.The manufacturing structure uses these component parts:The disassembly structure produces these disassembly component parts (each inventory part type is Disassembly Component):I have calculated the standard manufacturing costs for MW-M-103 in Cost Set 2 and copied to Cost Set 1 using the standard template M-110.Each Disassembly Component has cost template D-110, with Use Distribution Cost 'on', attached in all Cost Sets.When I performed the Disassembly Cost Calculation for MW-M-103 in Cost Set 2, no material costs from bucket 110 were distributed to the components, only operation costs. Should these material costs have been distributed to the Disassembly Components?From the documentation:The disassembly cost calculation is performed by Disassembly Cost Calculation. Before calculation of disassembly cost it is important that the cost for the disassembled product
Hi,Has anyone translated IFS Cloud into the Traditional Chinese Language? I know this is technically possible, but I am looking for someone that has actually done it.Thanks!
Dear all,Is there a way in IFS Cloud to assign shop order operations and allocate labour hours to individual employees, rather than assigning them to a labour class?If so, could you advise on the functionality or configuration required to support this? Thank you and kind regards,Samiru
Hello Lovely people,I have spotted unusual issue with IFS. We have BOM structure as per below.Item A- Sub con process ( Item type purchased)Item A1-Sub con process ( item type purchased)we use item type “purchased” for Sub con process.here itemA1 is child part of itemA. Now After MRP run I could only see the demand generated for “Item A “ only.. However “ ItemA1” does not show any demand?I am not sure if anyother MRP set up needs to be done in order to allow both item to be planned in IFS?I came across below set up in “ Inventory Part” Screen? What is the importance of this field ? is it auto populate by IFS or someone need to do manually?
Hello,I would like to know whether there is a parameter in IFS that allows the configuration of a pattern for automatically generated Part Numbers when creating an Engineering Part.For example, if I enter only "test" in the Part Description field and leave the Part Number blank, IFS generates a Part Number such as 100025.Is it possible to configure this automatic numbering scheme so that generated Part Numbers follow a specific format, for example:MAT-000001 MAT-000002 MAT-000003or any other prefix + sequence pattern?If so, where can this be configured in IFS Cloud?Thank you for your help.
So we have a situation where we are trying to adjust the On Hand Qty of a part that is sitting in an Arrival type location. Somehow after this part was received and subsequently moved out of the arrival location, a very small quantity than 1 (see 1st screenshot) remained in the Arrival location and now we cannot adjust it out. We have tried doing an inventory issue as well as a count per inventory part but the arrival location does not show up as a location we can do the adjustment for. We have tried backing out that quantity from the PO which was somehow cancelled, but we couldn’t do it. As you can see from the second screenshot, somehow IFS performed a move for 3029.xxxxxx. And I kinda why the On Hand Qty that was left behind is what it is. This part in Inventory Part had the Qty Calc Rounding set at 16. How do we get rid of the 0.0000000000000001 qty.
Hi all,Building a CTO proof of concept on IFS Cloud 25R1 and hitting an issue I can't pin down.SetupConfigurable part created, Configurable = Yes, linked to a Configuration Family Configuration Family has Configure By Category enabled, with 7 categories and characteristics assigned to each 12 characteristics: a mix of Discrete Option and Variable Value (numeric) 3 Configuration Formulas built and approved to Valid status Part Configuration Revision at revision 1, status Test, all 12 characteristics imported Configuration Structure exists but all rules removed for testing (in case of silent issue) No sales rules currently activeBehaviourLaunching Edit Configuration from an interim order works correctly. All category tabs render. I can enter values across the first three or four tabs but then the later categories have no chars. They can be added manually but then disappear. My first issue. Then If I remove configure by category I can enter all values (Discrete Options accept selection
Hello All,I have observed one thing which is different then other ERP system.We have various shop orders currently are in “ Released” status.. Our process is we review them daily and which ever necessary based on demand we reserve & Print them for shop floor to take act upon. My query is I have see various shop orders as “ Released” status which does not have demand / no SS generated demand/ So other criteria based demand to have this shop order , why after MRP run system is not asking to “ Cancel” this shop orders like other ERP systems? I am still learning the IFS so still not sure where can I see such MRP based signales
Is there an option to set an Engineering Revision not to transfer until the Revision status is Released? There is no other way to check whether Approval completed, all required documents is attached, etc. before the transfer.
Hi,I hope that you are well.Shop order forward load is not visible against the individual Person on the Resource Analysis page, but the forward load is visible for each employee in relation to work tasks.Is there any way within the system which we can plan at individual level to assess the demand (from shop orders) vs their available capacity?Or is there a way in which we can somehow manually populate the "shop order hours" column in the resource analysis screen? Thank you for looking into this. Kind regards,Samiru
In 26R1, was there a way to adjust the available capacity when a Work Center was unavailable for a number of days?Ideally, we're looking for a way to set the available capacity to 0 for the specific days when the Work Center is not available.
Good afternoon, We are trying to revoke project disconnection for purchase order lines. User are allowed to connect to projects just not disconnect.How do I do this?Thanks!
When calculating projected balance, system ignores plan purchase requisitions, if it falls within the Planning Time Fence (PTF). Is this intended behavior?
Issue Description: An issue occurs when creating an MRB case from the Shop Floor Workbench (Dispatch List). Although the MRB case is created successfully, the application becomes stuck on the "Enter and View Results" screen within the Control Plan, preventing users from continuing or interacting further with the page.Due to this behavior, users are unable to proceed with workshop activities and demonstrate the expected business process flow, which is impacting ongoing project validations and progress.Environment: IFS CLOUD 25R2Test Plan:Step 1: Create a Shop Order with an Active Control Plan status, enter the required Need Date, and release the Shop Order after assigning an operation number to a material line.Example: Shop Order 213204, Site X.Step 2: Open Shop Floor Workbench, filter by Shop Order 213204, select the operation line with quality controls defined (Operation 30), and create an analysis from the Control Plan menu.Step 3: Open Enter Inspection Results, enter a valid result
Hello,Just wanted to take the opportunity to highlight the new MRP Parts page in 26R1. I am pretty sure all MRP lovers “out there” will appreciate this entry into MRP result :-) It has a lot of good useful columns and it is a good starting point for drilling down to other material planning pages.And if you are not afraid of writing advanced queries you can for example find parts that has Late Order(s) OR Early Order(s) OR Remove Order(s) message like belowGood Luck with MRP planning-Mats
Hello, We are receiving an error ‘All created Analysis must be confirmed or cancelled before the operation no 10 is closed’ when trying to approve an operation on the shop floor workbench in IFS Cloud 25R2. This was the confirmed analysis associated with the operation. Why would this error be happening? Thank you. Thanks,Jay
Hi,We have strange situation in apps 10 with manufactured parts. FIFO is valuation method for all kind of parts.Despite identical material (bacflush costs) and labor costs being recorded across the period, inventory receipts from the same shop order (SO 325985) are reflecting progressively higher unit costs. Material issues and operation reports are auto-backflushed at receipt creation Multiple receipts from SO 325985 exhibit incrementally escalating unit costs (ranging from 0.1501 to 1.0610 per unit) Material composition and labor standards remain consistent across all receipts within the period (12–13 March 2025)Any thoughts how to investigate this issue?
Already have an account? Login
No account yet? Create an account
Enter your E-mail address. We'll send you an e-mail with instructions to reset your password.