We are using IFS Apps 9 and rely on the Shop Floor Workbench to clock in time for shop orders. Currently, when sharing time, users select multiple shop orders and click “Start Production” to allocate time across multiple orders with the same work center.

However, when attempting to job onto multiple shop orders with different work centers, the “Start Production” option is greyed out. Is there a setting or configuration that would allow users to share their time across different shop orders with different work centers?

We appreciate your guidance on this

Tharindu Illangasinghe
Superhero (Partner)
Forum|alt.badge.img+15

Hi ​@agovindarajan,

 

As per the below help text it is not possible.

 


Björn Hultgren
Hero (Employee)
Forum|alt.badge.img+23

This is possible from apps 10. Then  you have the option to group start operations in parallel rather than in sequence which will split the crew size / resource share rather than the time.