Hello,

 

What page can I use to view work order costs against a list of work orders, without running a report?

 

Thanks

Cory

Best answer by Thilini Kumarasinghe

Hi,

Can you try this option ?

In the Work Task Cost page, you can query for the task numbers in a particular work order/wwork orders and get the results.

Best Regards,

Thilini

View original
Did this topic help you find an answer to your question?

4 replies

Thilini Kumarasinghe
Ultimate Hero (Employee)
Forum|alt.badge.img+21

Hi,

Can you try this option ?

In the Work Task Cost page, you can query for the task numbers in a particular work order/wwork orders and get the results.

Best Regards,

Thilini


Cory
Sidekick (Customer)
Forum|alt.badge.img+5
  • Author
  • Sidekick (Customer)
  • 21 replies
  • March 8, 2024

Thanks @Thilini Kumarasinghe, it seems we do not have that page turned on.

 

Will this do a date range of all work tasks regardless of status?


Cory
Sidekick (Customer)
Forum|alt.badge.img+5
  • Author
  • Sidekick (Customer)
  • 21 replies
  • March 8, 2024

I’m looking more for putting in a range of work order planned start dates and having a column there telling me what current planned costs are for that work order.


Thilini Kumarasinghe
Ultimate Hero (Employee)
Forum|alt.badge.img+21

Hi @Cory 

Yes, this will list the costs irrespective of the work task status. That means, if a work task has certain costs reported (in the work task > cost tab), those data will be displayed here.

When it comes to the date, we have the field “Created Date”. This is the date on which the record was created. Here you can search for an exact date or a date range as well.

 

Best Regards,

Thilini