Skip to main content
Solved

Best maintenance calendar setup for both corrective and preventive action


Andryis
Sidekick (Partner)
Forum|alt.badge.img+10
  • Sidekick (Partner)
  • 72 replies

I would like to use the same calendar (MAINT: Off on Saturdays and Sundays) for all maintenance organizations. It is used for both corrective maintenance and PM actions. However, there is an exception for preventive maintenance as the work is carried out according to a 24/7 calendar every day of the year.

When I use a maintenance organization on a PM action and add a new calendar (MAINTPREV: 365/24/7) in the PM action trigger, the calendar of the maintenance organization takes precedence.

The solution I found is to create dedicated maintenance organizations for PM actions with a MAINTPREV calendar. However, this is very cumbersome because there are more than 20 sites, and each site has 10 maintenance organizations.

I am looking for a solution that uses only one calendar (MAINT) for all maintenance organizations but calculates the dates of PM lines according to a 365/24/7 calendar.

Best answer by eqbstal

@Andryis I don't get it. When a date is calculated based upon 365/24/7 the calculated date could be on a Saturday or Sunday. The connected work order and its tasks would not be able to ‘understand’ the date as it doesn't fit in the working week days.

Is it not possible to think of a replication job (in IFS10 available under migration jobs) that will copy over the information from one 'main’ calendar to the others?

View original
Did this topic help you find an answer to your question?

2 replies

eqbstal
Superhero (Partner)
Forum|alt.badge.img+21
  • Superhero (Partner)
  • 677 replies
  • Answer
  • June 26, 2023

@Andryis I don't get it. When a date is calculated based upon 365/24/7 the calculated date could be on a Saturday or Sunday. The connected work order and its tasks would not be able to ‘understand’ the date as it doesn't fit in the working week days.

Is it not possible to think of a replication job (in IFS10 available under migration jobs) that will copy over the information from one 'main’ calendar to the others?


EqeRobertK
Superhero (Partner)
Forum|alt.badge.img+15
  • Superhero (Partner)
  • 231 replies
  • June 30, 2023

HI @Andryis ,

I do not really understand why it should be cumbersome to change the applicable maintenance organisations to a different calendar. That is the way how IFS is expecting it.

Tha field calendar on the PM Action is only used to omit lines in the maintenance plan (see the help text of that field).

As you mentioned that there are 20 sites and 10 maintenance organistaions per site, that does not sound that much. It is only setting the correct calendar the the maintenance organisation once and then the sysrtem will calculate the plan accordingly.

As also mentioned by @eqbstal, you should also be aware that the execution on teh work task should also allow the 24/7 calendar.

So in my opinion is is only changing the basic settings once.

Please let me know if I do not understand why you think this is cumbersome.

Good luck,

Robert


Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings