service order completion in mobility when 2 activities Hi, A service order is created with 2 activities, dispatched to the same technician. Without using mobile work flow (moe -10100 unchecked), the technician can do the “stop work” on the 1st activity and go to the “completion” block at the bottom of the page to sign for example and exit from the service order. But with using the mobile work flow (for example moe -10117 set like this : details,start work,items,materials,checklists,stop work,completion), after having done “stop work” on the first activity, the technician is obliged to click on “start work” on the 2nd activity and complete this 2nd activity before beeing able to access to the “completion” block. Is there a way, with using mobile Work Flow, to go to the completion block after having done the “stop work on the first activity ? Thanks for your feedback