Good day,
In a new project for 300 devices (projects 7 in total), we have and will have a situation where one warehouse index will be ordered for the entire project.
Therefore, costs should be assigned to each of the seven projects, and currently it looks like this: "common" indexes are mainly attached to the first wagon of one of the projects, which disrupts the costs on the projects.
We tested the method of attaching the product/index structure, but when generating later, the system does not calculate the full 1 piece, but 1.000000000000001 and it would have to be changed manually each time.
Is there another solution for this?