Is it possible to skip requisition and create PO, when Customer order line with supply code is ‘Purch Order Trans’ and Customer order is released.

Best answer by Lumini Sahabandu

Hi @Manjunath Gowda ,

It is not possible to skip Purchase Requisition if the supply code of the customer order is :   ‘Purch Order Trans’. Purpose of having this supply code is to purchase that part through an external supplier. Thus the application has provided opportunity to either purchase it from a finalized supplier or to go through the supplier quotation process. Because of that it is mandatory to go through a PR when you are creating a PO.

Thank you,

Lumini.

View original
Did this topic help you find an answer to your question?

3 replies

Lumini Sahabandu
Hero (Employee)
Forum|alt.badge.img+10

Hi @Manjunath Gowda ,

It is not possible to skip Purchase Requisition if the supply code of the customer order is :   ‘Purch Order Trans’. Purpose of having this supply code is to purchase that part through an external supplier. Thus the application has provided opportunity to either purchase it from a finalized supplier or to go through the supplier quotation process. Because of that it is mandatory to go through a PR when you are creating a PO.

Thank you,

Lumini.


Forum|alt.badge.img+1

Thanks for the reply, I was expecting if we can create PO to Primay supplier directly. Something similar to ‘Order processing Type’


Forum|alt.badge.img+7
  • Hero (Partner)
  • 50 replies
  • November 25, 2022

Your not able to bypass the Purchase Requisition Stage but you can automate the creation of the PO as long as there aren’t any Authorisation Rules in place to stop the PR proceeding. 