Activity Grouping Demand (UoM)


robert_g
Sidekick (Customer)
Forum|alt.badge.img+7

Hi,

Is there a way of preventing requisitions being grouped when demand is added. So, instead of 1 requisition being created with a quantity of 24. Instead 3 individual requisitions would be created (20/2/2) for an activity. 

Thanks,

R

2 replies

EqeRobertK
Superhero (Partner)
Forum|alt.badge.img+15
  • Superhero (Partner)
  • 231 replies
  • July 12, 2022

Hi @robert_g,

It is the whole idea behind MRP to combine the quantities. The system will make sure the supply will provide enough inventory for the demand. It is possible to create manually a supply based on the demand, so these will have a hard link and MRP will not take this into account.

In case the demand is created from a project activity, then you can also use PMRP (Project MRP). This will combine the quantities per project activity. Hope that can also help you out.

 

BR,

 

Robert


EqeRobertK
Superhero (Partner)
Forum|alt.badge.img+15
  • Superhero (Partner)
  • 231 replies
  • July 12, 2022

Also use the online help text