Hello Experts!

Posting this question again because I haven’t received any replies earlier.

I am currently facing problem related to Work Orders (In project structure with resources attached for man-hour calculation) progress, which is not getting calculated from Work Tasks Progress % , furthermore I have double checked all the relevant field required to calculate the progress of the Work Order (pictures attached) Kindly tell me if I am missing out any thing or it is any thing else.

Any help in this regard will highly be appreciated.

Note: All the attached picture are of the same Work Order.

Work Progress in Work Tasks
Progress Template
Template Connection with Work Order
Work Progress in Active Work Order

@Affan Ahmed What is your expectation. Percentages are either 0 or 100%. Next to this, what is the status of the tasks? Are there 5 tasks connected to the work order or more? Test with 5% on task status Under Preparation, 10% on Prepared etc. play around with the tasks and their statusses.


@Affan Ahmed What is your expectation. Percentages are either 0 or 100%. Next to this, what is the status of the tasks? Are there 5 tasks connected to the work order or more? Test with 5% on task status Under Preparation, 10% on Prepared etc. play around with the tasks and their statusses.

@eqbstal In the above scenario we have 5 work task with Status “Work done” having 100% progress so the work order must reflect 100% cumulative progress because all tasks are 100% but in contrast it’s showing 0% progress as shown in the last attachment.


@Affan Ahmed What is your expectation. Percentages are either 0 or 100%. Next to this, what is the status of the tasks? Are there 5 tasks connected to the work order or more? Test with 5% on task status Under Preparation, 10% on Prepared etc. play around with the tasks and their statusses.

@eqbstal As you can see in the above Progress Template only Work Done , Reported , Finished have 100% cumulative Progress & in other statuses i.e. Under Preparation , Prepared etc. the value is 0 where we can manually enter the work progress & that manually entered Progress should also be reflect on the overall work progress of Work Order clearly which is not getting calculated in this case.