MRP for Customer Owned Inventory

  • Jul 9, 2020 11:21 PM UTC
  • 2 replies
  • 262 views

Forum|alt.badge.img+4

Hello Community,

 

We are using Apps 9 UD 15. A majority of our sites are managing and consuming Customer Owned Inventory. Is there a way that MRP can be used to coordinate a PULL system for this inventory?

 

Thank you in advance.

 

Regards

Ken

2 replies

Boma
Do Gooder (Partner)
Forum|alt.badge.img+1
  • Do Gooder (Partner)
  • Jul 15, 2020 1:55 PM UTC

Dear Ken,

 

I think you can use Perform Planning Network MRP to calculate the requirement for all your sites. But you need to setup some Planning Network Data which contain Sites that you want to include in the MRP Calculation.

 

 


Forum|alt.badge.img+4
  • Author
  • Sidekick (Customer)
  • Jul 20, 2020 4:48 AM UTC

Dear Boma,

 

Thank you for this suggestion. I will conduct some further investigations.

 

Kind regards

 