Baseline a Project - Activity and Subproject Level

  • April 14, 2020
  • 1 reply
  • 476 views

Forum|alt.badge.img+5

Baseline a Project - Activity and Subproject Level

I though IFS 10 gave us the capability to BASELINE planned hours/cost on a project at both the subproject and activity level. Is that not the case? We can only seem to do it at the project level.

Best answer by Sumedha

Baseline can only be created at project level even in IFS APP 10 but you can see the baseline cost at any level when it is created.

 

-Sumedha

View original
Did this topic help you find an answer to your question?

1 reply

Sumedha
Do Gooder (Partner)
Forum|alt.badge.img+5
  • Do Gooder (Partner)
  • 11 replies
  • Answer
  • April 17, 2020

Baseline can only be created at project level even in IFS APP 10 but you can see the baseline cost at any level when it is created.

 

-Sumedha