Solved

Baseline a Project - Activity and Subproject Level

  • 14 April 2020
  • 1 reply
  • 400 views

Userlevel 4
Badge +5

Baseline a Project - Activity and Subproject Level

I though IFS 10 gave us the capability to BASELINE planned hours/cost on a project at both the subproject and activity level. Is that not the case? We can only seem to do it at the project level.

icon

Best answer by Sumedha 17 April 2020, 09:17

View original

1 reply

Userlevel 1
Badge +5

Baseline can only be created at project level even in IFS APP 10 but you can see the baseline cost at any level when it is created.

 

-Sumedha

Reply