Flexible WO generation - Condition Based


Forum|alt.badge.img+3
  • Do Gooder (Customer)
  • 6 replies

We have a situation where we use condition-based PM actions to generate WOs for objects based on run hours.   
For example, let’s say the condition is set up as below.

 


So, the maintenance plan is predicted and generated as below.  All good. 
 

Practically, these objects are not getting serviced when the exact value reached.  So, the actual value or run hours on the work task performed date can be lower or higher. 
Let’s assume that we perform the maintenance at 175 hours.  So ideally the next WO generation should happen 375 hours.  But the system waits till 400 hours for automatic generation.   We can track the actual performed value using generated value and last value fields, but the automatic generation does not consider the actual performed value. No changed to the planned value. 
Is there any option in IFS to have this catered? 
 

Best answer by dhwe

Hi,

Isn’t the “Performed Value Based” option on the Condition , together with the “Last measurement at maintenance” option working for this situation?

BR.

 

View original
Did this topic help you find an answer to your question?

2 replies

dhwe
Sidekick (Partner)
Forum|alt.badge.img+5
  • Sidekick (Partner)
  • 5 replies
  • Answer
  • October 23, 2023

Hi,

Isn’t the “Performed Value Based” option on the Condition , together with the “Last measurement at maintenance” option working for this situation?

BR.

 


Forum|alt.badge.img+3
  • Author
  • Do Gooder (Customer)
  • 6 replies
  • October 23, 2023

@dhwe  Yes and thanks Dharshana.  