Hi
I am fairly new to IFS Apps 10 and would like to know how to stop operations from scheduling to start in parallel in the same work centre?


Within this work centre we only have 2 shop floor employees and have tried to replicate this by setting the ‘resource quantity for calculation’ 2 and set the ‘capacity calculation bases’ to group.
How do it get it to schedule so the same operation doesn't plan to start in parallel?
regards
Jamie