Skip to main content
Question

Receive Into Arrival, Perform Putaway


Forum|alt.badge.img+9
  • Sidekick (Customer)
  • 74 replies

Hello,

I have configured the putaway feature and I am able to generate transport tasks using the “Refill All Putway Zones” function but when I attempt to use the “Receive Into Arrival, Perform Putaway” at time of register arrivals I get this message 

“No putaway location could be found for 1000 ea of Part 70-050598-00, Revision 2 currently stored at Location 3045". 

Is there another configuration that needs to be done for receiving? Thanks.

8 replies

Forum|alt.badge.img+2
  • Do Gooder (Partner)
  • 4 replies
  • May 13, 2024

Hi Mitchell Moss,

Please check if you have setup basic data in following windows,

Basic Data

  • Warehouse Navigator
    • Putaway Control for warehouse
    • Capacities and capabilities
  • Storage Zones
  • Putaway Zone Basic Data
  • Inventory Part -->
    • Putaway Zones --> Inventory Values and Operative Values
    • Storage Requirement --> Capability Requirement

 

Thank you,
Dhananjani Palliyaguru


Piyal Perera
Hero (Employee)
Forum|alt.badge.img+9
  • Hero (Employee)
  • 245 replies
  • May 13, 2024

Hi @mmoss 

It's quite challenging to provide a response without examining your data. Typically, this error message suggests there's a specific issue with your data that's causing the putaway logic to struggle in identifying a location.

Please ensure that the warehouse you're receiving items in has NOT been designated as a Putaway Destination.

To pinpoint the exact problem, consider beginning with basic putaway zone settings, perhaps starting with just one storage zone.

regards,

Piyal


Forum|alt.badge.img+7
  • Sidekick (Employee)
  • 48 replies
  • June 27, 2024

Recreated errors with parts 1-PR-PT, 1-PR-PT2 and 1-PR-PT3 in R&D’s Apps10 REGIONAL TEST LKP. Case owner from IFS Support will log this to R&D.


Piyal Perera
Hero (Employee)
Forum|alt.badge.img+9
  • Hero (Employee)
  • 245 replies
  • June 28, 2024

Hi @Roy Almeida

   I accepted this support case and will have closer look about the issue.

 

regards,

Piyal


Forum|alt.badge.img+7
  • Sidekick (Employee)
  • 48 replies
  • June 28, 2024

Thanks @Piyal Perera 


Forum|alt.badge.img+2
  • Do Gooder (Employee)
  • 2 replies
  • February 24, 2025

Hi ​@mmoss,
I hope this issue is resolved now. However, responding to this will be helpful for someone in the future.

Make sure the inventory location (picking location) that you define in the warehouse navigator attached to the storage zone you defined.  Refer the screen shots and make sure these basic data are setup. 


 

 

 

Regards,

Dulani. 


Forum|alt.badge.img+9
  • Author
  • Sidekick (Customer)
  • 74 replies
  • February 24, 2025

@DUWELK I am able to perform “Refill All Putway Zones” so the configuration is complete. I am not able to execute “Receive Into Arrival, Perform Putaway” for the same part number. What is the outcome of the support ticket?


Piyal Perera
Hero (Employee)
Forum|alt.badge.img+9
  • Hero (Employee)
  • 245 replies
  • February 26, 2025

Hi ​@mmoss

   Several months ago I investigated this issue and had discussions with our consulting team. I explained the problem is related to data setup. After a few days I closed the issue since no more questions raised. Do you still have the issue?

 

regards,

Piyal