Skip to main content

Hello,

When I have a released purchase requisition created from MRP that needs authorization, but the authorization step is not executed before MRP run again, the released requisition is getting blowen away and a new planned requisition is created.  Is some set up missing that the released requisition requiring authorization is getting deleted and a new planned requisition created or is this the expected results?

Best, 
Dolly  

Hi,

If you require the Released Purchase requisitions to remain and be included as supply for MRP you need to check the below setting on Site/ Manufacturing Tab 

 

 

 

This will ensure that any ‘Released’ po’s are not deleted when re planning processes.

 

Hope this helps

Kind regards

 

Deb


Reply