Is there a way to update Change Request when connected CO in Approved state ?
Or What is the method to get the Change Order from Approved to Preliminary or Analyzed
Engineering>PDM>Change Management

Hi Guys,
Is there a way to update Change Request when connected CO in Approved state ?
Or What is the method to get the Change Order from Approved to Preliminary or Analyzed
Engineering>PDM>Change Management
Best answer by Pabasara Kalahe
Hi,
When the state of the CO is changed to Approved, the state of all the connected CRs will automatically be changed to Processed.
When a CR goes into Processed state, that means a CO has been issued for this CR.
Once the status is updated, the status change is irreversible.
Hope this helps.