Change Request how to update Approved or Processed CR

  • July 12, 2021
  • 1 reply
  • 319 views

Forum|alt.badge.img+4

Hi Guys,

Is there a way to update Change Request when connected CO in Approved state ?

Or What is the method to get the Change Order from Approved to Preliminary or Analyzed

Engineering>PDM>Change Management

 

Best answer by Pabasara Kalahe

Hi,
 

When the state of the CO is changed to Approved, the state of all the connected CRs will automatically be changed to Processed. 

When a CR goes into Processed state, that means a CO has been issued for this CR. 


Once the status is updated, the status change is irreversible.

 

Hope this helps.

 

/Pabs

View original
Did this topic help you find an answer to your question?
This topic has been closed for comments

1 reply

Pabasara Kalahe
Hero (Employee)
Forum|alt.badge.img+7

Hi,
 

When the state of the CO is changed to Approved, the state of all the connected CRs will automatically be changed to Processed. 

When a CR goes into Processed state, that means a CO has been issued for this CR. 


Once the status is updated, the status change is irreversible.

 

Hope this helps.

 

/Pabs