Hello,

 

Is it possible to modify the activity ID when receiving a PO.

 

Thank you for your help.

 

Christophe.

 

 

Best answer by Abdul

Hi ​@DMTCCAN,

No, it is not possible to change the Project information while receiving the Purchase Order. 

Please change at the Purchase Order level before registering the arrival.

 

Regards

Abdul Rehman

View original
Did this topic help you find an answer to your question?

3 replies

Abdul
Superhero (Partner)
Forum|alt.badge.img+17
  • Superhero (Partner)
  • 402 replies
  • Answer
  • May 22, 2025

Hi ​@DMTCCAN,

No, it is not possible to change the Project information while receiving the Purchase Order. 

Please change at the Purchase Order level before registering the arrival.

 

Regards

Abdul Rehman


DMTCCAN
Sidekick (Customer)
Forum|alt.badge.img+6
  • Author
  • Sidekick (Customer)
  • 15 replies
  • May 22, 2025

Thank you Abdul !

 

Do you mean that the user has to go back to the PO screen and change at this level !

 

Regards

 

Christophe.

 

 


Abdul
Superhero (Partner)
Forum|alt.badge.img+17
  • Superhero (Partner)
  • 402 replies
  • May 22, 2025

@DMTCCAN, Yes, the user needs to go back to the PO screen to update the Project connection.