Hello,
Could you please let me know if the steps described below are capturing expected behaviour? please notice column comments.
I was expecting the planned cost to get updated after the changed in the PURQ (Purchase Requisition) price but the Planned Cost has not changed (row 5 in table)
ID | Action | Prj Materials & Services window (value) | Prj Monitoring window
| Comment |
1 |
Add demand line (MISC. PARTS)
|
10,000 |
Planned Cost = 10,000
|
|
2 |
Create Project Supply Request |
10,000 |
Planned Committed Cost = 10,000 |
|
3 |
Create PURQ |
10,000 |
Planned Cost = 10,000 Planned Committed Cost = 10,000 |
|
4 |
Update Price Manually in PURQ (Change Price/Curr from 10 to 20) |
10,000 |
Planned Cost = 10,000 Planned Committed Cost = 20,000 |
At the time of creating the PURQ the price of the provider of the external services has changed, hence the manual update on the PURQ |
5 |
Update Planned Cost & Hours in the demand line |
10,000 |
Planned Cost = 10,000 Planned Committed Cost = 20,000 |
There is no changes in the Planned Cost. The original value remains despite the Update action |
Many thanks for your advice
Miguel