PSO ARP Resource Skills options

  • March 5, 2025
  • 1 reply
  • 14 views

Forum|alt.badge.img+9

Hello,

 

Can anyone provide some context and detail on the Skills options/settings in the PSO ARP please?

 

How are the “In use costs” and In use multipliers” best used?

What are their designed use cases?

What are the recommended settings for trial usage?

 

I am hoping they can help us solve an issue:

 When we need to utilize a large crane truck, we hope to add more similar (crane dependent) work onto that same run for the day. This should of course be balanced against excessive travel distances to achieve similar work, but when using such a vehicle, it pays to maximise its specialist application, and then perhaps not use it at all on other runs. This would be better than needing to use the large crane truck every day for just 1 crane specific job a day. While other service work which does not require a crane truck can be done from that large crane asset, it is a better use of vehicles to use them primarily for their designed function.

Thanks

 

1 reply

Alexander Heinze
Superhero (Employee)
Forum|alt.badge.img+23

For the scenario you described I would rather look at shift cost. If the large crane truck has a higher shift cost that regular ones, “normal” jobs would be assigned to regular trucks.

The same would happen if you use different cost per hour, however if you have jobs that require the large crane truck, the shift cost would lead to more bundling on one day as opposed to only having one job per day across multiple days.


Reply