PM Action created based on a specific date

  • October 31, 2022
  • 1 reply
  • 55 views

Emre.IFS
Do Gooder
Forum|alt.badge.img+2

Hello everyone.

I have PM Actions that I create every 3 months. But I would like work orders to occur 1 week before the scheduled or due date.

For example PM due date :  31/03/2022

Wo Generation date : 23/02/2022

So I want WO automatic one week in advance.

Thanks for help.

 

1 reply

  • Superhero (Employee)
  • 1426 replies
  • November 4, 2022
Emre.IFS wrote:

Hello everyone.

I have PM Actions that I create every 3 months. But I would like work orders to occur 1 week before the scheduled or due date.

For example PM due date :  31/03/2022

Wo Generation date : 23/02/2022

So I want WO automatic one week in advance.

Thanks for help.

 

You should be able to setup the PM Calendar Generation background job to achieve this. 
Try to set Start Date to sysdate and Stop Date to sysdate+7 and set the job to run daily.

 

 