Hi Experts,

on screen of project navigator early start date of each activity changed automatically i.e 03-03-2024 changed with 01-01-2016. what is reason why this was change automatically. is there any impact from other screen/form please suggest solution.

 

 

Regards,

Waqar 

Best answer by TimeMarBou

Hello,

The Early Start Date is the planned start date of the activity.

If the activity is part of a project schedule and the critical path method is utilized, Early Start is the earliest date the activity can start based on the schedule logic, the present date and constraints.

 

Regards.

View original
Did this topic help you find an answer to your question?

1 reply

TimeMarBou
Hero (Partner)
Forum|alt.badge.img+9
  • Hero (Partner)
  • 103 replies
  • Answer
  • June 11, 2024

Hello,

The Early Start Date is the planned start date of the activity.

If the activity is part of a project schedule and the critical path method is utilized, Early Start is the earliest date the activity can start based on the schedule logic, the present date and constraints.

 

Regards.