we are testing Project Delivery when components are manufactured in different sites.

We would like to know what is the IFS solution for the semi-finished material movement in one activity or multiple activities.

  1. components are manufactured in different site, but within the same activity.
  2. components are manufactured in different site, but in different activity.

the semi-finished part 30-120 how to move from site 2 to site 1 in the above 2 scenarios?

attached the diagram illustrated in the above 2 scenarios.

Hi Ron,

I am faced with the same challenge of planning material movement related to project deliverable items

  1.  within the site (bay 1 to bay 2)
  2. between sites

These are very bulky items, that require special equipment / cranes to move them and need to be planned in advance.

Did you find a solution for your problem?
Thanks!

Malik