Closed PO under Unfinished Activity Work?

  • January 31, 2022
  • 0 replies
  • 98 views

Asela Munasinghe
Superhero (Customer)
Forum|alt.badge.img+23

When the user is trying to close the project, they can see the following. There are 2 POCOs, both in ‘POUpdated’ status with regards to the original PO. 

 

 

What must be done? Please advise. 