Solved

Can't change early finish date of an Activity

  • 17 January 2022
  • 4 replies
  • 218 views

Userlevel 4
Badge +9

can't change early finish date of an Activity, although we had modified the required dates on all the existing demands to be in line with the desired finish date

 

 

icon

Best answer by Dilan Senevirathne 23 January 2022, 12:41

View original

4 replies

Userlevel 5
Badge +13

Hi @SMANUEL 

Can you provide  a screen shot of the “Demand” tab. Make sure you capture the “Required Date” field

Best Regards,
Tharaka.

Userlevel 4
Badge +9

@Tharaka Senevirathne Thank You for the response..

Earlier we had modified the Required dates of all the existing demands on this particular Activity, to be within the Early Start & Finish dates..

To our surprise, we were able to change the dates the very next day!!

Thanks Much

Userlevel 5
Badge +13

Hi @SMANUEL 

If the required dates of all the demand lines are within the Early Start & Finish dates, I believe this issue needs in depth investigation. Hence creating a ticket to IFS support is the best solution I can think of.

Best Regards,
Tharaka.

Userlevel 4
Badge +9

@Tharaka Senevirathne will do that next time ..Thanks Much

Reply