can't change early finish date of an Activity, although we had modified the required dates on all the existing demands to be in line with the desired finish date
Best answer by Dilan Senevirathne
View originalcan't change early finish date of an Activity, although we had modified the required dates on all the existing demands to be in line with the desired finish date
Best answer by Dilan Senevirathne
View originalHi
If the required dates of all the demand lines are within the Early Start & Finish dates, I believe this issue needs in depth investigation. Hence creating a ticket to IFS support is the best solution I can think of.
Best Regards,
Tharaka.
Earlier we had modified the Required dates of all the existing demands on this particular Activity, to be within the Early Start & Finish dates..
To our surprise, we were able to change the dates the very next day!!
Thanks Much