The customers that am working with raised the following question. Would like to request your feedback and advice to assist the customer.
Description: Project Gantt Performance Issues
- To move one activity without saving or scheduling takes 1 minutes and 9 seconds a time. 3 minutes to save saving before scheduling; 1 minute to schedule on only 4 activity changes and a further 3 minutes 17 seconds to save the scheduled changes. Effectively looking at up to 9-10 minutes per overall change and the business currently makes daily changes due to various reasons. If I had to move 120 linked activities that would be 2 hours work?!
Test Scenarios:
- Open a Project in Gantt view
- Move Activity and Save
- Schedule Project and Save