Question
One manufacturing work center , registered in two sites, how to plan shop order operations ?
There are more than one occasions that I have come across that our users define one physical machine in 2 sites expecting to plan shop order operations seamlessly. But this set up sometime leads to very confusing consequences.
Example :
Company : A
Site : X
Site : Y
Expensive CNC machine is installed in Site X ( defined as a manufacturing work center in Site X as "CNC-X").
But this usually runs under capacity ( lets assume that both sites runs on 8 hr calendar). So The company decides that they can put some shop orders registers in Site Y to be done in the under utilized work center in Site X.
Therefore it is decided to define the work center in site Y as " CNC-Y" in IFS.
Now lets assume that the manufacturing planner has access to both site X and site Y shop order operations.
If you run CRP, since in IFS , CNC is 2 distinct work centers, the capacity available is 8 hr each. Which is not really the case. For both sites , the available hours are 8 in total per day.
In such setup planners need be vigilant to not to overload the "common " machine for both sites. Manufacturing visualizer and loading Advance Planning Board with resource break reflecting loads on the "other" site might help. But in any case, 2 work centers represent one single physical CNC machine which is not true. Generic resoruce may be a ( distant ) complete solution.
Q1. Is it a common practice that the assets are defined in that way?
Q2: In such setup, what are the approaches that planners has take to take best use of IFS Planning functions?
Q3. Anyone has any suggestions or best practices to recommend for such situations ?
your comments are appreciated.
Example :
Company : A
Site : X
Site : Y
Expensive CNC machine is installed in Site X ( defined as a manufacturing work center in Site X as "CNC-X").
But this usually runs under capacity ( lets assume that both sites runs on 8 hr calendar). So The company decides that they can put some shop orders registers in Site Y to be done in the under utilized work center in Site X.
Therefore it is decided to define the work center in site Y as " CNC-Y" in IFS.
Now lets assume that the manufacturing planner has access to both site X and site Y shop order operations.
If you run CRP, since in IFS , CNC is 2 distinct work centers, the capacity available is 8 hr each. Which is not really the case. For both sites , the available hours are 8 in total per day.
In such setup planners need be vigilant to not to overload the "common " machine for both sites. Manufacturing visualizer and loading Advance Planning Board with resource break reflecting loads on the "other" site might help. But in any case, 2 work centers represent one single physical CNC machine which is not true. Generic resoruce may be a ( distant ) complete solution.
Q1. Is it a common practice that the assets are defined in that way?
Q2: In such setup, what are the approaches that planners has take to take best use of IFS Planning functions?
Q3. Anyone has any suggestions or best practices to recommend for such situations ?
your comments are appreciated.
Reply
Enter your E-mail address. We'll send you an e-mail with instructions to reset your password.