Hi,
First of all, I’m using IFS version 7.5.
I have 8 operations for a part number and the actual manufacturing lead time is 1 day.
However, IFS calculated lead time is 2.22 days.
The reason is IFS assumed that these operations are running in sequence one by one.
That’s mean after Ops 10 completed 1500pcs, then only start Ops 20; after Ops 20 completed 1500pcs, then only start Ops 30 and so on....
But in actual situation, Ops 20 will be started once Ops 10 completed 20pcs for example.
Since Ops 10 - 80 are not running in parallel, I tried to configure CBS Overlap. However, CBS Overlap does not impact manufacturing lead time.
Can anyone let me know how can I overcome this to shorten the manufacturing lead time?
Is there any setting to allow IFS 7.5 consider the CBS Overlap into the manufacturing lead time?
Thank you.
Best Regards,
KS Eng