Skip to main content
Question

Apps 10 Project Time Reporting


Forum|alt.badge.img+3

Does anyone know if it is possible to record future time against a project i.e. If it was Tuesday to log Wednesday’s time?

Shehan Almeida
Superhero (Partner)
Forum|alt.badge.img+18

Hi Kate,

 

Yes. You can do project time reporting for  future periods using the Time Registration Window .

 

It will update the time card day and the project transactions accordingly with proper configuration.

 

 

Best Regards,

Shehan Almeida.


Forum|alt.badge.img+3

Hi Shenan,

Is there a way to prevent people reporting to future periods without the use of a custom event?

Thanks


Shehan Almeida
Superhero (Partner)
Forum|alt.badge.img+18

Hi Kate,

 

I am afraid to say that I am not aware of any method of blocking this in a user friendly manner.

 

You can update the Valid to date of the given ‘Report Codes’ to current date every day.  Then employee cant report time for future periods. However, as I said it will not be a very practical solution. 

 

Best Regards,

Shehan Almeida.

 

 


Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings