Question

Substitute Variable in scheduled database taks

  • 10 April 2024
  • 0 replies
  • 11 views

Userlevel 4
Badge +9
  • Sidekick (Customer)
  • 76 replies

Hi all,

 

I previously had a topic on this, which lead to looking into the NLS settings, but unfortunately not found a solution yet. So hope someone has some valueable input for this.

We have a scheduled database task for the Supplier Payment Proposals, in which we use a “substitute variable”, being Start of Next week. However, the created Proposal, has start of next week as Sunday, and not as Monday.

When i manually create a Supplier Payment Proposal, it does take Monday as the First Day of Next Week. 


 

 

We have changed the NLS Setting for the Database Processes to Danish, set the Database Settings to Danish as well as the Server settings. But nothing seems to have any impact on the scheduled database tasks behaviour.


0 replies

Be the first to reply!

Reply