Question for App 9
Summary
When you have PO charge lines related to a specific PO line (via ‘Connect to Line’ & ‘Connect to Release’), is there any way to inherit some of the code part values from the line?
Specific case:
We use code part ‘C’ to define the WO number from Service&Maintenance. In this way, every WO related GL entry has the WO value in code part ‘C’ and we can analyze our accxoutn up to WO level. So far so good, but…
The WO number is filled automatically on the PO lines created from requisitions in a workorder. When we need to define extra charges on the PO that are related to a specific line, we do this by using the ‘Connect to Line’ and ‘Connect to release’ fields. Unfortunately it seems there is no possibility to automatically inherit the value of code part C of the connected PO line to the charge.
Thanks for any advice on how to solve this issue !
Luc.