How to add unassigned tasks in schedule board map


Forum|alt.badge.img+4

I can only see a task which has been assigned to an Engineer in schedule board map, but can not see unassigned task in map?

Any specific reason ?

 

3 replies

Alexander Heinze
Superhero (Employee)
Forum|alt.badge.img+23

Can you share a screenshot - is this FSM, IFS Cloud Dispatch Console or PSO?


Forum|alt.badge.img+4
  • Author
  • Do Gooder (Customer)
  • 10 replies
  • April 3, 2023

Its FSM only.


Forum|alt.badge.img+3

Hi, 

I have recreated the steps allowing to see the task on the map.

 

First: Unassigned task at it appears on the task list below the schedule board gantt
Second: Dragged the task (4181) from task list to drop it on the gantt
Last Step: Task 4181 appears on the map on the extreme upper left whilst being in Unassigned status.

 

Hope it helps.

 

Thank you!