Good afternoon;
I’m testing a scenario whereby a client has a purchase order with staged payments. Some of the staged payments have already been approved and paid to the supplier. The client now needs to change the part number on the purchase order ( due to a revision ). Is it possible to “undo” the staged payment approval and generate a credit memo against the supplier for the amount already paid? Or is it possible to apply the amount already paid to the staged billing of the replacement PO line? I’m a bit stumped.
Thank you in advance!