IFS apps 10 - Planned Receipt Date on Purchase Order


Forum|alt.badge.img+1

In IFS apps 10 Planned Receipt Date is fetched from Purchase Requisition Wanted Receipt Date.

When using Route ID (for example Monday delivery) the Planned Receipt Date is not recalculated when turning Purchase Requisition into Purchase Order and is not showing the actual available date for consumption in Inventory Part Availability Planning. Planned Receipt Date will be the frozen date from Purchase Requisition Wanted Receipt Date and is not in connection with the Planned Arrival Date. There can be even 4 days difference between Planned Arrival and Planned Receipt Date.

How are other apps 10 users solving this issue?

2 replies

eqbstal
Superhero (Partner)
Forum|alt.badge.img+21
  • Superhero (Partner)
  • 675 replies
  • May 28, 2020

KatrinL,

I've not run in that sort of trouble, but I think that I would raise an LCS case at IFS to see if this is a bug. My logic sense says it is. Otherwise the Route ID would have no real meaning on the PO.

Steve


ALHAGMO
Hero (Customer)
Forum|alt.badge.img+10
  • Hero (Customer)
  • 69 replies
  • August 17, 2022

Hi Katrin,

we are having the same issue and try to find a solution.

Did you get a solution  in the meantime?

Thank you for your feedback!

Regards

Martina