Skip to main content
Solved

Perido Planning (MRP Code G) and Master Scheduling


Vernon Anderson
Sidekick (Employee)
Forum|alt.badge.img+8

I’ve just been posed a question to which I don’t have an answer.  What happens to the master scheduling calculation if the inventory part is set to period part planning?  Will it aggregate demand for the order cover time period s that code G does in MRP?

 

Thanks!

Best answer by matt.watters

Hi Vernon,

Check out this post.

https://community.ifs.com/supply-chain-251/planing-method-g-order-cover-time-manufactured-parts-35301

View original

matt.watters
Superhero (Partner)
Forum|alt.badge.img+25

Vernon Anderson
Sidekick (Employee)
Forum|alt.badge.img+8

Thanks, Matt.  I thought I was losing it!


Rhillson
Sidekick (Customer)
Forum|alt.badge.img+5
  • Sidekick (Customer)
  • March 1, 2024

@matt.watters @Vernon Anderson - I replied on the linked post above as well, but I’m curious if either of you had any leads on future official development to address this limitation and/or knew partners you could suggest who had successfully worked around it to provide an MS output like “G” planning does for MRP.


Reply