Solved

Can the available quantity in 1 HU be moved to another existing HU directly?

  • 27 April 2022
  • 1 reply
  • 114 views

Userlevel 4
Badge +9

Hi All,

Can the quantity (full or partial) available in 1 HU be moved to another existing HU directly? If so, can you please list down the steps?

Thanks in advance.

Regards,
Arunalu
 

icon

Best answer by Chamath Kuruppuarachchi 24 June 2022, 09:36

View original

1 reply

Userlevel 4
Badge +9

Hi Arunalu,

As per my understanding there is no functionality to move handling unit partially or fully directly to another handling unit.

We can only un-attach the qty in HU and attach them to a new one. I think practical scenario will be the same as well. We have to remove cargo from the existing pallet before moving to a new pallet.

 

Thanks,

BR,

Chamath

Reply