Solved

Work Assignment Time Report calculation

  • 14 October 2022
  • 1 reply
  • 84 views

Userlevel 5
Badge +14

Hi,

Using MWO with IFS Cloud 22R1, I noticed that the “Actual Worked Hours” are calculated using “Assignment Finish” date and time.

Is it the expected behavior ?

It make more sense to me that it would be calculated with “Work Finish” date and time.

Kind regards,

Lénaïc

icon

Best answer by Thommy 14 October 2022, 13:46

View original

1 reply

Userlevel 5
Badge +12

Hi Lénaïc,

You are correct in your observation, this is not correct behavior.

This has been corrected in 22R1 SU6 by correction https://ifsdev.atlassian.net/browse/AMZWOP-7119