Hi,
I have a requirement where Work Tasks should be Bundled together for ease of Scheduling but still require the ability to flexibly change the status of the Bundled Work Tasks individually - is this possible using MWO in 25R2? See example below.
Bundle Task 1
- Work Task 1
- Work Task 2
Bundle Task 1 is then assigned to a Technician and executed on MWO.
Question - can the technician update the status of Work Task 2 to something like Incomplete and marking Work Task 1 and Bundle Task 1 as Work Done?
Thanks
Tom