Hello Community!
I hope you are all doing well my simple question is that lets suppose we have a sales contract in which we have to built 2 individual boat.
1-So will we create 2 different projects?
OR
2-Create 1 project with 1 Project Navigator and create 2nd project as a sub-project in the first project navigator.
Reason for asking this question is that we receive only one payment from client per milestone i.e. “steel cutting” 25% how will we divide the payment on both project
Note: Both Projects have different scheduling activities