How can I get intersite cost to update on receipt? We want to automatically update the purchase price on Site#1 with the cost from Site#2. The part on Site#1 is setup as an intersite purchased part from Site#2 where the part is setup as Manufactured part and using standard labor costs. The PO and CO and Shop ordes are processed properly.But the costs we captured in Manufacturing with raw materials and labor time are only on Site#2. Is there a process that will update the price on Site#1 when the PO is received with the cost value from Site#2?
We currently have to manually update pricing on Site#1.
Thank you